HEAD START CENTER DESIGN GUIDE
Table
of Contents | Chapter:1
| 2 | 3 | 4
| 5 | 6 | 7
| 8 | 9 | 10
| Appendix: A | B | C
| D | Selected References
Appendix A: Commonly Used Terms for Center Development Projects
Sections: A
| B | C | D | E
| F | G | H | I
| J | L | M |N
|O| P | Q | R
| S | T | V | W
| Z
These terms, phrases, and definitions are used by architects, engineers,
contractors, and managers in construction projects. Those involved in
center development may need to be familiar with construction terminology.
- Abate or abatement:
- To remove material.
- Abstract of title:
- An outline history of the ownership of a parcel of land from the original
grant, with changes in title, and with a statement of all mortgages,
liens, or encumbrances affecting the property.
- Acceptance test:
- A test conducted by a purchaser (or his or her agent) to determine
if the material, devices, or equipment delivered conform to the purchase
contract specifications or the product supplied by the vendor.
- Access:
- A means of approach, e.g., a road, street, or walk.
- Accessible:
- Allowing physical contact, as by means of an easily removable cover
or door, or a part of the building structure or finish materials. Providing
access to a fixture, appliance, or piece of equipment; removal of a
cover, panel, plate, or similar obstruction may be required.
- Accident:
- A sudden, unexpected event identified as to time and place.
- Acre:
- A unit of land measurement equal to 43,560 sq. ft. or 4046.85 sq.
m.; 1 sq. mile (2.59 sq. km.) equals 640 acres.
- Activity:
- A task or item of work that must be performed in order to complete
a project.
- Activity duration:
- An estimation of the amount of time required to accomplish an activity.
- ADD:
- On drawings, abbreviation for addendum.
- Addendum:
- A supplement to bidding documents, issued prior to the submission
of bids, for the purpose of clarifying, correcting, or adding to the
specifications previously issued.
- Addition:
- A floor or floors, a room, a wing, or other expansion to an existing
building, or any new construction that increases the height or floor
area of an existing building or adds to it, such as a porch or attached
garage. An amount added to the contract sum by a change order.
- Additional services:
- The professional services that may, upon the owner's request or approval,
be rendered by the architect in addition to the basic services identified
in the owner-architect agreement.
- Additive alternate:
- An alternate bid in an addition to the same bidder's base bid. Same
as alternate bid.
- Administration of the construction contract:
- Same as construction phase-administration of the construction contract.
- Administrative authority:
- The individual, official, board, department, council, or leader established
and authorized by a political subdivision created by law to administer
and enforce the provisions of the code.
- Advertisement for bids:
- The published public notice soliciting bids for a construction project.
Most frequently used to conform to legal requirements pertaining to
projects to be constructed under public authority, and usually published
in newspapers of general circulation in those districts from which the
public funds are derived.
- A/E:
- Abbreviation for architect-engineer.
- Agency:
- A relationship by which one party, usually the agency, is empowered
to enter into binding transactions affecting the legal rights of another
party, usually called the principal, by, for example, entering into
a contract or buying or selling property in the principle's name or
on the principal's behalf. An administrative branch of government.
- Agent:
- One who is empowered to enter into binding transactions on behalf
of another.
- Agreement:
- An arrangement indicating the intent of a contract, but not necessarily
fulfilling all the enforceable provisions of it. A meeting of minds.
A legally enforceable promise or promises between two or among several
persons. On a construction project, the document stating the essential
terms of the construction contract that incorporates by reference the
other contract documents.
- Agreement form:
- A document setting forth in printed form the general provisions of
an agreement, with spaces provided for inserting specific data relating
to a particular project.
- AIA:
- Abbreviation for American Institute of Architects.
- All-in contract:
- Same as turn-key job.
- Alterations:
- Remodeling.
- Alternate bid:
- The amount stated in the bid to be added to or deducted from the amount
of the base bid if the corresponding change in project scope or alternate
materials and/or methods of construction is accepted.
- American bond:
- Same as common bond.
- Application for payment:
- The contractor's written request for payment of amount due for completed
portions of the work. This may include, if the contract so provides,
materials delivered and suitably stored pending their incorporation
into the work.
- Appraisal:
- An evaluation or estimate (preferably by a qualified professional
appraiser) of the market or other value, cost, utility, or other attribute
of land or other facility.
- Approved:
- Referring to materials, devices, or construction accepted by the authority
having jurisdiction, by reason of tests or investigations conducted
by it or by an agency satisfactory to the authority, or by reason of
accepted principles or tests by national authorities or technical or
scientific organizations.
- Approved equal:
- Materials, equipment, or methods approved by the architect for use
in the work as acceptable as an equivalent in essential attributes to
the material, equipment, or methods specified in the contract document.
- Approving authority:
- The individual agency, board, department, or official established
and authorized by a political subdivision created by law to administer
and enforce specified requirements.
- Arbitration:
- The binding resolution of disputes by one or more neutral persons,
as a substitute for judicial proceedings; may be invoked only by agreement
of the parties to the dispute. Such agreement may be arrived at before
there is an actual dispute - for example, through a clause in a contract.
- Architect:
- A person trained and experienced in the design of buildings and coordination
and supervision of all aspects of the construction of buildings.
- Architect-engineer:
- An individual or firm offering professional services as both architect
and engineer; term generally used in government contracts, particularly
those involving the federal government.
- Architect's approval:
- The architect's written or imprinted acknowledgment that materials,
equipment, or methods of construction are acceptable for use in the
work.
- Architect's scale:
- A scale having graduations along its edges so that scale drawings
can be measured directly in feet.
- Architectural:
- Pertaining to architecture, its features, characteristics, or details.
- Architectural drawing:
- One of a number of drawings prepared by an architect for a construction
project, e.g., plans, elevations, and details.
- Architecture:
- The art and science of designing and building structures, or large
groups of structures, in keeping with aesthetic and functional criteria.
- Area method:
- A method of estimating the probable total construction cost by multiplying
the adjusted gross floor area by a predetermined cost per unit of area.
- Article:
- A subdivision of a document.
- Assessed valuation:
- The value of a property as determined by a recognized legal entity
for real estate tax purposes; often this valuation is less than the
true market value of the property.
- Assessment:
- A tax, charge, or levy on property.
- Assessment ratio:
- Of a property, the ratio between its market value and its assessed
value.
- Assignment:
- The transfer of a legal right.
- Attorney-in-fact:
- A person authorized to act for or on behalf of another person or organization,
to the extent prescribed in a written instrument known as a power of
attorney.
- Authority:
- Same as administrative authority.
- Authority having jurisdiction:
- A federal, state, or local entity having statutory authority. In
many instances the delegated agent assumes the role of the authority
with jurisdiction.
- Base bid:
- The amount of money stated in the bid as the sum for which the bidder
offers to perform the work, not including that work for which alternate
bids are also submitted.
- Base bid specifications:
- The specifications listing or describing only those materials, equipment,
and methods of construction upon which the base bid must be predicated,
exclusive of any alternate bids.
- Base services:
- The services performed by an architect during the following five phases
of a project: schematic design; design development; construction documents;
bidding or negotiation; and contract administration.
- Bid:
- An offer to perform the work described in a contract at a specified
cost. A complete and properly signed proposal to do the work. Competition
for a job based on lowest cost to do the work. Bids are generally cost
specific, based on the cost of labor, materials, profit, and overhead.
Bids are normally not negotiated and can not be changed once accepted
by the owner. Bids are time sensitive and are generally good for 30
to 60 days after the bid opening.
- Bid bond:
- A form of bid security executed by the bidder as principal and by
a surety.
- Bid date:
- The date established by the owner or the architect for the receipt
of bids.
- Bidder:
- One who submits a bid for a prime contract with the owner, as distinct
from a sub-bidder who submits a bid to a prime bidder. A bidder is not
a contractor on a specific project until a contract exists between him
and the owner.
- Bid documents:
- The advertisement or invitation to bid, instructions to bidders, the
bid form, and the proposed contract documents, including any addenda
issued prior to receipt of bids.
- Bidding or negotiation phase:
- The fourth phase of the architect's basic service, during which competitive
bids or negotiated proposals are sought as the basis for awarding a
contract.
- Bidding period:
- The calendar period beginning at the time of issuance of bidding requirements
and contract documents and ending at the prescribed bid time.
- Bidding requirements:
- Those documents providing information and establishing procedures
and conditions for the submission of bids. They consist of the notice
to bidders or advertisement for bids, instructions to bidders, invitation
to bid, and sample forms.
- Bid form:
- A form furnished to a bidder to be filled out, signed, and submitted
as his bid.
- Bid guarantee:
- Same as bid security.
- Bid letting:
- Same as bid opening.
- Bid opening:
- The opening and tabulation of bids submitted by the prescribed bid
time and in conformity with the prescribed procedures.
- Bid price:
- The sum stated in the bid for which the bidder offers to perform the
work.
- Bid security:
- The deposit of cash, certified check, cashier's check, bank draft,
money order, or bid bond submitted with a bid and serving to guarantee
to the owner that the bidder, if awarded the contract, will execute
such contract in accordance with the bidding requirements and the contract
documents.
- Bid time: The date and hour established by the owner or the architect
for the receipt of bids.
- Bona fide bid:
- A bid submitted in good faith, complete and in prescribed form which
meets the conditions of the bidding requirements and is properly signed
by someone legally authorized to sign such bid.
- Bond:
- A financial guarantee by a surety company that work will be completed
as described in a contract.
- Bonding capacity:
- An indication of a contractor's credit rating.
- Bonus and penalty clause:
- A provision in a construction contract for payment of a bonus to the
contractor for completing the work prior to a stipulated date, and a
charge against the contractor for failure to complete the work by such
stipulated date.
- Boundary survey:
- A mathematically closed diagram of the completed peripheral boundary
of a site, reflecting dimensions, compass bearings, and angles.
- Builder's risk insurance:
- A specialized form of property insurance to cover work in the course
of construction. Also property insurance.
- Building area:
- The total area of the site that is covered by buildings as measured
on a horizontal plane at ground level.
- Building code:
- A collection of rules and regulations adopted by authorities having
appropriate jurisdiction to control the design and construction of buildings,
alteration, repair, quality of materials, use and occupancy, and related
factors of the buildings within their jurisdiction.
- Building inspector:
- A member of a building department, usually of a municipality, who
inspects construction to determine if it conforms to both the requirements
of the building code and the approved plans.
- Building permit:
- A written authorization to an applicant for a specific project allowing
him to proceed with construction; granted by the authorized agency,
a tribe, or local municipality having jurisdiction after plans have
been filed and reviewed.
- Building rehabilitation:
- The returning of a building to a useful state by repair, alteration,
and modification.
- Building restoration:
- The accurate reestablishment of the form and details of a building,
its artifacts, and the site on which it is located, usually as it appeared
at a particular time.
- Building restriction:
- Any one of a number of restrictions imposed on the construction of
a building or the use of land. Also known as restrictive covenant.
- Building services:
- The utilities and services supplied and distributed within a building
generally related to the building environment.
- Building site:
- Same as site.
-
- Cash allowance:
- An amount established in the contract documents for inclusion in the
contract sum to cover the cost of prescribed items not specified in
detail, with provision that variations between such amount and the finally
determined cost of the prescribed items will be reflected in change
orders appropriately adjusting the contract sum.
- Certificate for payment:
- A statement from the architect to the owner confirming the amount
of money due to the contractor for work accomplished, or for materials
and equipment suitably stored, or both.
- Certificate of insurance:
- A memorandum issued by an authorized representative of an insurance
company stating the types, amounts, and effective dates of insurance
in force for a designated insured.
- Certificate of occupancy:
- A document issued by governmental authority certifying that all or
a designated portion of a building complies with the provisions of applicable
statutes and regulations, and permitting occupancy for its designated
use.
- Certification:
- A declaration in writing that a particular product or service complies
with a specification or stated criterion.
- Change order:
- A written order to the contractor signed by the owner and the architect
issued after the execution of the contract, authorizing a change in
the work or an adjustment in the contract sum or the contract time as
originally defined by the contract document. It may add to, subtract
from, or vary the scope of work. A change order may be signed by the
architect alone, provided he has written authority from the owner.
- Changes in work:
- Changes ordered by the owner consisting of additions, deletions, or
other revisions within the general scope of the contract, the contract
sum and the contract time being adjusted accordingly.
- Clerk of the works:
- Same as project representative.
- Closed list of bidders:
- Same as invited bidders.
- Closed specifications:
- Specifications stipulating the use of specific products or processes
without provision for substitution. Same as base bid specifications.
- Code:
- A legal instrument adopted within a political jurisdiction that prescribes
the minimum acceptable levels of the design, construction, installation,
and performance of materials, components, devices, items of equipment,
appliances used in a building, or building system and/or subsystem.
- Code of practice:
- A technical document setting forth standards of good construction
for various materials and trades.
- Community:
- People having common rights, privileges, or interests, or living in
the same place under the same laws and regulations.
- Compensation:
- Payment for services rendered or products or materials furnished or
delivered.
- Completed operations insurance:
- Liability insurance coverage for injuries to persons or damage to
property occurring after an operation is completed, and attributed to
that operation. The insurance does not apply to damage to the completed
work itself.
- Completion bond, construction bond, contract bond:
- The guarantee of a bonding company that a contractor will perform
and deliver the work contracted free of all encumbrances and liens.
- Completion date:
- In the contract documents, the date of substantial completion of the
work.
- Completion list:
- Same as inspection list.
- Comprehensive general liability insurance:
- A broad form of liability insurance covering claims for bodily injury
and property damage which combines under one policy coverage for all
liability exposures on a blanket basis and automatically covers new
and unknown hazards that may develop. It automatically includes contractual
liability coverage for certain types of contracts.
- Comprehensive services:
- Professional services performed by the architect in addition to the
basic services in such related areas as project analysis, programming,
land use studies, feasibility investigations, financing, construction
management, and special consulting services.
- Conditions of the bid:
- Conditions set forth in the instructions to bidders, the notice to
bidders or advertisement for bids, the invitation to bidders, or other
similar bid documents prescribing the conditions under which bids are
to be prepared, executed, submitted, received, and accepted.
- Conditions of the contract:
- Those portions of the contract documents which define, set forth,
or relate to the following: contract terminology; the rights and responsibilities
of the contracting parties and of others involved in the work; requirements
for safety and compliance with laws and regulations; general procedures
for the orderly prosecution and management of the work; payments to
the contractor; and similar provisions of a general, non-technical nature.
- Consent of surety:
- Written consent of the surety on a performance bond and/or labor and
material payment bond to contract changes, such as change orders or
reductions in the contractor's retainage, final payment, or waiving
notification of contract changes.
- Construction:
- All the on-site work done in building or altering structures, from
land clearance through completion, including excavation, erection, and
the assembly and installation of components and equipment.
- Construction bond:
- A completion bond.
- Construction budget:
- The sum established by the owner as available for construction of
the project, or the highest acceptable bid.
- Construction cost:
- The cost of all the construction portions of a project. This is generally
based upon the sum of the construction contracts and other direct construction
costs. It does not include the compensation paid to the architect and
consultants, the cost of land, right-of-way, or other costs defined
in the contract documents as being the responsibility of the owner.
- Construction documents:
- The working drawings and specifications.
- Construction documents phase:
- The third phase of the architect's basic services. In this phase the
architect prepares from the approved design development documents, for
approval by the owner, the working drawings and specifications and the
necessary bidding information. In this phase the architect also assists
the owner in the preparation of bidding forms, the conditions of the
contract, and the form of agreement between the owner and the contractor.
- Construction inspector:
- Same as project representative.
- Construction loan:
- A loan to a builder for a short-term, financing of construction prior
to permanent financing.
- Construction management:
- The special management services performed by the architect or others
during the construction phase of the project, under separate or special
agreement with the owner. This is not part of the architect's basic
services, but is an additional service sometimes included in the comprehensive
services.
- Construction phase - administration of the construction contract:
- The fifth and final phase of the architect's basic services, which
includes the architect's general administration of the construction
contract.
- Construction survey:
- Same as engineering survey.
- Consultant:
- An individual or organization engaged by the owner or the architect
to render professional consulting services complementing or supplementing
the architect's services.
- Contingency allowance:
- A sum designated to cover unpredictable or unforeseen items of work,
or changes subsequently required by the owner.
- Contingency agreement:
- Any agreement under which the rights or obligations of a party are
subject to the happening of stated contingency.
- Contract:
- A legally enforceable promise or agreement between two or more persons.
- Contract administration:
- The duties and responsibilities of the architect or consultant during
the construction phase.
- Contract bond:
- Same as completion bond.
- Contract date:
- Same as date of agreement.
- Contract documents:
- Those documents that comprise a contract, including: the owner-contractor
agreement, conditions of the contract, plans and/or drawings, specifications,
all addenda, modifications, and changes together with any other items
stipulated as being specifically included.
- Contracting officer:
- The person designated as the official representative of the federal
government with specific authority to act on behalf of the government
in connection with the project.
- Contractor:
- One who undertakes responsibility for the performance of construction
work, including the provision of labor and materials, in accordance
with plans and specifications and under a contract specifying cost and
a schedule for completion of the work; the person or organization responsible
for performing the work and identified as such in the owner-contractor
agreement.
- Contractor's affidavit:
- A certified statement of the contractor, properly notarized, relating
to payment of debts and claims, release of liens, or similar matters
requiring specific evidence for the protection of the owner. Same as
non-collusion affidavit.
- Contractor's estimate:
- A forecast of construction cost, as opposed to a firm proposal, prepared
by the contractor for a project or a portion of a project.
- Contractor's liability insurance:
- Insurance purchased and maintained by the contractor to protect him
from specified claims which may arise out of or result from his operations
under the contract, whether such operations are by him, by any subcontractor,
or by anyone directly or indirectly employed by either, or by anyone
for whose acts the contractor or subcontractors may be liable.
- Contractor's option:
- A provision of the contract documents under which the contractor may
select certain specified materials, methods, or systems at his own option,
without change in the contract sum.
- Contractor's proposal:
- Same as bid.
- Contract sum:
- The price stated in the owner-contractor agreement, which is the total
amount payable by the owner to the contractor for the performance of
the work under the contract document. This can be adjusted only by a
signed change order.
- Contract time:
- The period of time established in the contract document pursuant to
other agreements between the parties, or by operation of law, within
which the work must be completed.
- Contractual liability:
- Liability assumed by a party under a contract by express language,
implication, or operation of law. A "hold harmless" clause.
- Cost breakdown:
- Same as schedule of values.
- Cost-plus-fee agreement:
- An agreement under which the contractor or the architect is reimbursed
for his direct and indirect costs and, in addition, is paid a fee for
his services. The fee is usually stated as a stipulated sum or as a
percentage of cost.
- CPM:
- Abbreviation for critical path method.
- Critical path method:
- CPM, a system of project planning, scheduling, and control which combines
all relevant information into a single master plan, permitting the establishment
of the optimum sequence and duration of operations. It contains the
interrelation of all the efforts required to complete a construction
project and includes the efforts critical to timely completion of the
project.
-
- Damages:
- Same as liquidated damages.
- Date of agreement:
- The date stated on the face of the agreement. If no date is stated,
it may be the date on which the agreement is actually signed, if this
is recorded, or it may be the date established by the award. This date
is also referred to as the contract date.
- Date of commencement of the work:
- The date established in a notice to proceed, or, in the absence of
such notice, the date of the agreement, or another date established
by the concerned parties.
- Date of substantial completion:
- The date certified by the architect when the work or a designated
portion of the work is sufficiently complete in accordance with the
contract documents so the owner may occupy or use the designated portion
as intended.
- Debt service:
- The periodic payment of a loan, including both accrued interest and
a portion of the principal.
- Deduction:
- The amount deducted from the contract sum by a change order.
- Deductive alternate:
- A substitute bid resulting in a deduction from the bidder's base bid.
This is the same as an alternate bid.
- Deed:
- Any duly attested, written document executed under seal and delivered
to effect a transfer, bond, or contract, such as a conveyance of real
property or interest in the property.
- Deed restriction:
- A limitation on the use of land, which is set forth in a deed conveying
the restrictions.
- Defective work:
- Work not complying with the contract requirements.
- Demolition:
- The systematic destruction of a building, all or in part.
- Department of Housing and Urban Development:
- Same as HUD.
- Deposit for bidding documents:
- Monetary deposit required to obtain a set of construction documents
and bidding requirements, customarily refunded to bona fide bidders
on return of the documents in good condition within a specified time.
- Design:
- To compose a plan for a building. The architectural concept of a building
as represented by plans, elevations, renderings, and other drawings.
- Design development phase:
- The second phase of the architect's basic services. In this phase
the architect prepares the design development documents consisting of
drawings and other documents to fix and describe the size and character
of the entire project, including structural, mechanical, and electrical
systems, materials, and such other essentials as may be appropriate.
The architect also submits to the owner a further statement of probable
construction cost.
- Design documents:
- Same as structural design documents.
- Detailed estimate of construction costs:
- A forecast of construction costs prepared on the basis of a detailed
analysis of materials and labor for all items of work, as contrasted
with an estimate based on current area, volume, or similar unit costs.
- Developed area:
- An area of land upon which improvements have been made.
- Development:
- A tract of previously undeveloped land that is subdivided and provided
with all necessary utilities, such as roads, water, electricity, sewers,
etc.
- Direct personnel expense:
- Salaries and wages of principals and employees engaged on a project,
assignment, or task, including mandatory and customary benefits.
- Document deposit:
- Same as deposit for bidding documents.
-
- Educational occupancy:
- The use of a building or buildings for gathering groups of six or
more persons for purposes of instruction.
- Eminent domain:
- The power or right of the nation or state to take private property
for public use, usually with reasonable compensation to the owner.
- Employer's liability insurance:
- Insurance protection for the employer against claims by employees
for damages which arise out of injuries or diseases sustained in the
course of their work and which are based on common law negligence rather
than on liability under workmen's compensation acts.
- Engineer:
- A person trained and experienced in the profession of engineering;
a person licensed to practice the profession by the authority in the
area.
- Engineering survey:
- A survey conducted to obtain essential information for planning an
engineering project or developing and estimating its cost.
- Environmental design professionals:
- The professionals collectively responsible for the design of man's
physical environment.
- Environmental impact statement:
- A detailed analysis of the probable environmental consequences of
proposed federal legislation, major federal actions, or large-scale
construction making use of federal funds likely to significantly affect
environmental quality; such a statement is required by the National
Environmental Policy Act of 1969.
- Estimate:
- Same as detailed estimate of construction costs. Same as statement
of probable construction costs. Same as contractor's estimate.
- Extended coverage insurance:
- Same as property insurance.
- Extra services:
- Same as additional services.
- Extra work:
- Any work not included in the contract documents, an extra.
-
- Facility:
- The building(s), playground(s), parking area(s), and campus where
the program or construction site is located.
- Fee-plus-expenses agreement:
- Same as cost-plus-fee agreement.
- Field representative:
- Same as project representative.
- Field supervision:
- That portion of the architect's supervisory work done at the construction
site.
- Final acceptance:
- The owner's acceptance of a project from the contractor upon certification
by the architect that it is complete and in accordance with the contract
requirements. Final acceptance is confirmed by making final payment,
unless otherwise stipulated at the time of making such payment.
- Final completion:
- The completion of work and all contract requirements by the contractor.
- Final inspection:
- The final review of the project by the architect prior to his issuance
of the final certificate for payment.
- Final payment:
- Payment made by the owner to the contractor of the entire unpaid balance
of the contract sum as adjusted by change orders upon issuance by the
architect of the final certificate for payment.
- Fire and extended coverage insurance:
- Same as property insurance.
- Fixed limit of construction cost:
- The maximum allowable cost of the construction work as established
in the agreement between the owner and the architect. Same as construction
budget.
- Force account:
- A term used when work is ordered to be done without prior agreement
as to lump-sum or unit-price cost thereof, and is to be billed for at
the cost of labor, materials and equipment, insurance, taxes, etc.,
plus an agreed percentage for overhead and profit.
-
- General conditions:
- That part of the contract document that sets forth many of the rights,
responsibilities, and relationships of the parties involved. Same as
conditions of the contract.
- General contract:
- Under the single contract system, the contract between the owner and
the contractor for construction of the entire work.
- General contractor:
- The prime contractor who is responsible for most of the work at the
construction site, including that performed by the subcontractors.
- Generally accepted standard:
- A specification, code, rule, guide, or procedure in or related to
the field of construction that is recognized and accepted as authoritative.
- General requirements:
- The title of Division 1 of the American Institute of Architects'uniform
system for construction specifications, data filing, and cost accounting.
- Guarantee:
- A legally enforceable assurance of the quality or duration of a product
or of work performed.
- Guaranteed maximum cost:
- An amount estimated in an agreement between the owner and contractor
as the maximum cost of performing specified work on the basis of cost
of labor and materials plus overhead expense and profit.
- Guaranty bond:
- Same as bid bond. Same as labor and material payment bond. Same as
performance bond. Same as surety bond.
-
- HUD:
- The abbreviation for Department of Housing and Urban Development.
-
- Inspection list:
- A list of items of work to be completed or corrected by the contractor
during or after completion of the work and during the warranty period.
- Instructions to bidders:
- Instructions contained in the bidding requirements for preparing and
submitting bids for a construction project. Same as notice to bidders.
- Invitation to bid:
- A solicitation of competitive bids. The term usually is employed in
connection with private construction projects, but also may be used
for government projects, for the purchase of supplies or other goods,
or in connection with the sale of property. Same as advertisement for
bids.
- Invited bidders:
- The bidders selected by the architect and the owner as the only ones
from whom bids will be received.
-
- Job:
- Same as project. Same as work.
- Job captain:
- A member of the architect's staff normally responsible on a given
project for the preparation of drawings and their coordination with
other documents.
- Job site:
- The site of the construction project.
- Job superintendent:
- Same as superintendent.
-
- Labor and material payment bond:
- A bond of the contractor in which a surety guarantees to the owner
that the contractor will pay for labor and materials used in the performance
of the contract. The claimants under the bond are those having direct
contracts with the contractor or any subcontractor.
- Landscape architect:
- A person trained and experienced in the design and development of
landscapes and gardens.
- Land survey:
- A survey of landed property establishing or reestablishing lengths
and directions of boundary lines. Land boundaries are usually defined
by ownership, commencing with the earliest owners through successive
ownerships and partitions.
- Latest event occurrence time:
- The latest point in time by which no further work must be done on
an activity if the project is not to be delayed.
- Latest start date:
- The latest possible point in time by which an activity must be started
if the project is not to be delayed.
- Letter of intent:
- A letter signifying an intention to enter into a formal agreement,
usually setting forth the general terms of such agreement.
- Liability insurance:
- Insurance that protects the insured against liability on account of
injury to the person or property of another.
- Licensed architect:
- Same as architect.
- Licensed contractor:
- A person or organization certified by governmental authority, where
required by law, to engage in construction contracting.
- Licensed engineer:
- Same as professional engineer.
- Lien:
- A right enforceable against specific property to secure payment of
an obligation.
- Lien waiver:
- Same as waiver of lien.
- Life-cycle cost:
- The cost of a building or equipment based not only on the initial
expenditure but also on its maintenance and operating cost over its
entire lifetime.
- Liquidated damages:
- A sum specified in a contract whereby damages in the event of breach
are to be determined. In a construction contract, liquidated damages
usually are specified as a fixed sum per day for failure to complete
the work within a specified time.
- Listed:
- Equipment, materials, or products included in a list published by
an organization acceptable to the authority having jurisdiction.
- Loss-of-use insurance:
- Insurance protecting against financial loss during the time required
to repair or replace property damaged or destroyed by an insured peril.
- Lowest responsible bidder, lowest qualified bidder:
- The bidder who submits the lowest bona fide bid and is considered
to be fully responsible and qualified to perform the work for which
the bid is submitted.
- Lowest responsive bid:
- The lowest bid that is responsive to and complies with the bidding
requirements.
- Lump-sum agreement:
- Same as stipulated sum agreement.
-
- Main contractor:
- Same as general contractor.
- Maintenance bond:
- A bond that provides a guarantee to an owner that the contractor will
rectify defects in workmanship or materials reported to the contractor
within a specified time period following final acceptance of the work
under contract.
- Measured drawing:
- An architectural drawing of an existing structure, drawn to scale.
- Mechanic's lien:
- A lien on privately owned real property created by state statute in
favor of persons supplying labor or materials for a building or structure
or improvements thereof, generally for the value of the labor or materials
supplied by them.
- Model code:
- A proposed building code that is written and published by building
official associations available for adoption by states, counties, and
municipalities.
- Modification:
- A written amendment to the contract document signed by both parties.
A change order. A written order for a minor change in the work issued
by the architect.
- Modular construction:
- Construction in which a selected unit or module, such as a box or
other sub-component, is used repeatedly in the aggregate construction.
- Mortgage:
- A loan in which property is used as security for the debt.
- Mortgagee:
- The lender from whom a mortgage is obtained.
- Mortgage lien:
- A charge against property as security for the payment of a loan.
- Mortgagor:
- The borrower who obtains a mortgage.
-
- Negligence:
- Failure to exercise a degree of care that a reasonable and prudent
person would exercise under the same circumstances.
- Negotiation phase:
- Same as bidding or negotiation phase.
- Noncollusion affidavit:
- A notarized statement by a bidder that he has prepared his bid without
collusion of any kind.
- Nonconforming work:
- Work that does not fulfill the requirement of the contract documents.
- Notice to bidders:
- A notice contained in the bidding requirements informing prospective
bidders of the opportunity to submit bids on a project and setting forth
the procedures for doing so.
- Notice to proceed:
- Written communication issued by the owner to the contractor authorizing
him to proceed with the work and establishing the date of commencement
of the work.
-
- Observation of the work:
- A function of the architect in the construction phase, during his
periodic visits to the site, to familiarize himself generally with the
progress and quality of the work and to determine in general if the
work is proceeding in accordance with the contract documents.
- Occupancy permit:
- Same as certificate of occupancy.
- Opening of bids:
- Same as bid opening.
- Ordinance:
- A law or rule adopted by a local governmental authority.
- Orientation:
- The placement of a structure on a site with regard to local conditions
of sunlight, wind, and drainage.
- OSHA:
- Abbreviation for Occupational Safety and Health Administration, Department
of Labor.
- Over design:
- As applied to structural design, a design based on requirements higher
than service demands, usually as a means of compensating for unknown
or anticipated deficiencies.
- Owner:
- The architect's client and party to the owner-architect agreement.
- Owner-architect agreement: A contract between the architect and the
client for professional services.
- Owner-contractor agreement:
- A contract between the owner and contractor for a construction project.
- Owner's inspector:
- A person employed by the owner to inspect construction in the owner's
behalf.
- Owner's liability insurance:
- Insurance that protects the owner against claims arising from his
ownership of property and that may be extended to cover claims arising
from operations of others under the construction contract.
-
- Package dealer:
- A person or organization assuming responsibility under a single contract
for the design and construction of a project to meet the specific requirements
of another.
- Parcel:
- Of land, a contiguous land area that is considered as a unit, that
is subject to a single ownership, and that is legally recorded as a
single piece.
- Partial occupancy:
- Occupancy by the owner of a portion of a project prior to final completion.
- Partial payment:
- A progress payment.
- Payment request:
- Same as application for payment.
- P.E.:
- Abbreviation for professional engineer.
- Penal sum:
- The amount named in a contract or bond as the damage or penalty to
be paid by a signatory in the event he fails to perform his contractual
obligations or does not do so within the time prescribed by the contract.
- Penalty-and-bonus clause:
- Same as bonus-and penalty clause.
- Penalty clause:
- A contract provision setting forth the damages a party must pay in
the event of breach. If such a clause is regarded by the court as too
harsh to be regarded as a fair estimate of probable damages, it will
normally be held invalid. Same as liquidated damages.
- Percentage agreement:
- An agreement for professional services in which the compensation is
based upon a percentage of the construction cost.
- Percentage fee:
- Compensation based on a percentage of construction cost. Same as fee.
- Performance bond:
- A bond of the contractor in which a surety guarantees to the owner
that the work will be performed in accordance with the contract documents.
This is frequently combined with the labor and materials payment bond,
except where prohibited by statute.
- Permit:
- A document issued by a governmental authority having jurisdiction
to authorize specific work by the applicant.
- Personal injury:
- In insurance terminology, injury or damage to the character or reputation
of a person, as well as bodily injury. Person injury insurance usually
covers such situations. Same as bodily injury.
- Personal property:
- Movable and other property not classified as real property.
- PERT:
- Acronym for project evaluation and review technique.
- PERT schedule:
- A PERT chart of the activities and events anticipated in a work process.
Same as critical path method (CPM).
- Planning:
- The process of studying the layout of spaces within buildings and
of buildings and other facilities or installations in open spaces in
order to develop the general scheme of a building or group of buildings.
- Post-completion services:
- Additional services rendered after issuance of the final certificate
for payment, such as consultation regarding maintenance, processes,
systems, etc.
- Power of attorney:
- An instrument authorizing another to act as one's agent. Same as attorney-in-fact.
- Preliminary drawings:
- Drawings prepared during the early stages of the design of a project.
- Preliminary estimate:
- Same as statement of probable construction costs.
- Premises:
- Land and/or its appurtenances.
- Pre-bid conference or pre-bid walk-through:
- A meeting of any interested bidder, at the job site, giving an opportunity
to review the project and discuss any unclear design or programming
issues.
- Pre-qualification of prospective bidders:
- The process of investigating the qualifications of prospective bidders
on the basis of their competence, integrity, and responsibility relative
to the contemplated project.
- Prime contract:
- A contract between the owner and contractor for construction of a
project or a portion of a project.
- Prime contractor:
- The contractor on a project having a contract directly with the owner.
- Prime professional:
- Any person or firm having a contract directly with the owner for professional
services.
- Principal:
- One on whose behalf or in whose name binding transactions may be entered
into by another, usually called the agent.
- Production drawings:
- Same as working drawings.
- Professional adviser:
- An architect engaged by the owner to direct an authorized design competition
for the selection of an architect.
- Professional engineer:
- A designation reserved, usually by law, for a person or organization
professionally qualified and duly licensed to perform engineering services
such as structural, mechanical, electrical, sanitary, and civil.
- Professional liability insurance:
- Insurance designed to insure an architect or engineer against claims
for damages resulting from alleged professional negligence. Also known
as errors and omissions insurance.
- Professional's practice:
- The practice of an environmental design professional in which services
are rendered within the framework of recognized professional ethics
and standards.
- Program:
- A statement prepared by or for an owner, with or without an architect's
assistance, setting forth the conditions and objectives for a building
project, including its general purpose and detailed requirements, such
as a complete list of the rooms required, their sizes, and special facilities.
- Program evaluation and review technique (PERT):
- A management control technique applied to building construction. It
explains what must be done to complete construction by a given date.
- Progress chart:
- A chart prepared by a contractor and updated monthly. The principal
trades involved in the project are tabulated vertically and the scheduled
construction time is shown horizontally.
- Progress payment:
- A partial payment made during progress of the work for work completed
and/or materials suitably stored.
- Progress schedule:
- A diagram, graph, or other pictorial or written schedule showing proposed
and actual times of starting and completing the various work elements.
- Project:
- A construction undertaking, composed of one or more buildings, and
site improvements planned and executed in a fixed time period.
- Project budget:
- The sum established by the owner as available for the entire project,
including the construction budget, land costs, equipment costs, financing
costs, compensation of professional services, contingency costs, and
other similar established or estimated costs.
- Project cost:
- The total cost of a project, including professional compensation,
land costs, furnishings and equipment, financing, and other changes
as well as the construction cost.
- Project manager:
- A third party consultant or employee of the owner who works for the
owner and coordinates the activities of the project. Assists with the
development of specific strategies of the project (including bidding
and contracting), establishing time frames and benchmarks for the project,
hiring other professional services, reviewing plans and drawings and
making recommendations to the owners, monitoring the budget in all phases
of the project, working with all consultants, monitoring the day-to-day
work progress of the contractor, performing close-out activities, and
preparing for occupancy.
- Project manual:
- The manual prepared by the architect for a project, including the
bidding requirements, conditions of the contract, and technical specifications.
- Project representative:
- The architect's representative at the project site who assists in
the administration of the construction contract.
- Property:
- Any asset, real or personal.
- Property damage insurance:
- Part of general liability insurance covering injury to or destruction
of tangible property, including loss of use of the property resulting
from the damage.
- Property line:
- A recorded boundary of a plot.
- Property survey:
- Same as boundary survey.
- Proposal:
- A document prepared by an applicant for a contract and used to evaluate
the professional capabilities of a business, agency, or individual against
a set of criteria that may include previous working experience. The
content of the proposal may be weighted on a numerical scale using a
set of questions that allows the person or persons choosing the contractor
to determine the best business, agency, or individual to hire for a
specific job. Preference can be given to local or in-state businesses.
The proposal also includes the qualifications of the lead professional
and team that will be working on the project. Normally, a proposal does
not include the cost of services. Cost is generally a negotiated amount
after the competing proposals have been evaluated and ranked.
- Proposal form:
- Same as bid form.
- Public liability insurance:
- Insurance covering liability of the insured for negligent acts resulting
in bodily injury, disease, or death of other than employees of the insured,
and/or property damage.
-
- Quality assurance:
- The inspection, testing, and other relevant action taken to ensure
that the desired level of quality is in accordance with the applicable
standards or specifications for the product or work.
- Quality control:
- The inspection, analysis, and other relevant action taken to provide
control over what is being done, manufactured, or fabricated, so that
a desired level of quality is achieved and maintained.
- Quality survey:
- A detailed analysis and listing of all materials and equipment necessary
to construct a project.
- Quitclaim deed:
- A written instrument conveying the seller's interest in a property.
It makes no warranties or representations as to the nature of that interest
or to the absence of any limitations or restrictions on the property,
or even that the seller has any right to the property at all.
- Quotation:
- A price quoted by a contractor, subcontractor, material supplier,
or vendor to furnish materials, labor, or both.
-
- Real estate:
- Property in the form of land and all its appurtenances, such as buildings.
- Real property:
- Land, everything growing on it, and all improvements made to it.
- Realty Officer:
- An employee who assists the government in realty issues including,
but not limited to, disputes, developments, and assignments.
- Record drawings:
- Construction drawings revised to show significant changes made during
the construction process, usually based on marked-up prints, drawings,
and other data furnished by the contractor to the architect.
- Record sheet:
- On a construction job, a sheet or printed form for keeping a record
of materials delivered, number of men working at the various trades,
hours worked, and other information.
- Regulation:
- Any rule prescribing permitted or forbidden conduct, whether found
in legislation or in the actions of an administrative agency or federal
agency.
- Release of lien:
- An instrument executed by one supplying labor, materials, or professional
services on a project that releases his mechanic's lien against the
project property. Same as a mechanic's lien.
- Render:
- To create a mechanical drawing, including elevation and an indication
of shades and shadows.
- Resident engineer:
- A person representing the owner's interests at the project site during
the construction phase. This term is frequently used on projects in
which a governmental agency is involved.
- Resident inspector:
- Same as owner's inspector.
- Responsible bidder:
- Same as lowest responsible bidder.
- Restricted list of bidders:
- Same as invited bidders.
- Restriction:
- On land, an encumbrance limiting its use.
- Restrictive covenant:
- An agreement between two or more individuals, incorporated within
a deed that stipulates how land may be used.
- Retainage:
- A sum withheld from progress payments to the contractor in accordance
with the terms of the owner-contractor agreement.
- Retention:
- The withholding of a portion (usually 10 percent) of a periodic payment
to a contractor, by prior agreement, for work completed. The retention
is held in escrow for a stipulated time period after the acceptance
of the completed work by the architect and owner.
- Retention money:
- Same as retention.
- Right-of-way:
- Any strip of land, including surface and overhead or underground space,
that is granted by deed or easement for the construction and maintenance
of specified linear elements, such as power and telephone lines.
-
- Satisfaction:
- Cancellation of an encumbrance on real property, usually by payment
of the secured debt.
- Schedule:
- A detailed tabulation of components, items, or parts to be furnished.
- Schedules of values:
- A statement furnished by the contractor to the architect reflecting
the portions of the contract sum allotted to the work and used as the
basis for reviewing the contractor's application for a progress payment.
- Schematic design phase:
- The first phase of the architect's basic services. In this phase,
the architect consults with the owner to ascertain the requirements
of the project and prepares schematic design studies consisting of drawings
and other documents illustrating the scale and relationship of the project
components for approval by the owner. The architect also submits to
the owner a statement of probable construction costs.
- Schematic drawing:
- Same as schematic design phase.
- Scheme:
- The basic arrangement for an architectural composition. Primary sketch
for a design.
- Selected bidder:
- The bidder selected by the owner for discussion relative to the possible
award of the construction contract.
- Selected list of bidders:
- Same as invited bidders.
- Setback:
- The minimum distance between a reference line and a building, or a
portion thereof.
- Shop drawings:
- Drawings, diagrams, illustrations, schedules, performances charts,
brochures, and other data prepared by the contractor or any subcontractor,
manufacturer, supplier, or distributor, that illustrate how specific
portions of the work shall be fabricated and/or installed.
- Single contract:
- A contract for construction of a project under which a single prime
contractor is responsible for all the work.
- Site:
- An area or plot of ground with defined limits on which a building
or project is located or proposed to be located.
- Site investigation:
- An examination of the subsoil and surface of a site to obtain complete
information necessary for the design of foundations and structures on
them.
- Site plan:
- A plan of a construction site showing the position and dimensions
of the building to be erected and the dimensions and contour of the
lot.
- Special conditions:
- A section of the conditions of the contract, other than general conditions
and supplemental conditions, which may be prepared for a particular
project. This is the same as conditions of the contract.
- Special hazards insurance:
- Additional perils insurance to be included in property insurance.
- Specifications:
- A written document contained in the project manual describing in detail
the scope of work, materials to be used, methods of installation, technical
nature of materials, equipment construction systems, and standards and
quality of workmanship for a parcel of work to be place under contract.
This is usually used in conjunction with working drawings in building
construction.
- Standard:
- A document prepared by a recognized standard-setting organization
that prescribes methods and materials for the safe use and consistent
performance of specific technologies.
- Standards of professional practice:
- Statements of ethical principles promulgated by professional societies
to guide their members in the conduct of professional practice.
- Statement of probable construction cost:
- Cost forecasts prepared by the architect during the schematic design,
design development, and construction phases of basic services for the
guidance of the owner.
- Statute of limitations:
- A statute specifying the period of time within which legal action
must be brought for alleged damage or injury. The length of the period
varies from state to state and depends upon the type of legal action.
- Statutory bond:
- A bond, the form and contents of which are prescribed by statute.
- Stipulated sum agreement:
- A contract in which a specific amount is set forth as the total payment
for performance of the contract.
- Structural design documents:
- The plans, design details, and job specifications prepared by the
structural designer.
- Structural drawings:
- Drawings, usually prepared by a structural engineer, of the design,
and working drawings of a building's structure.
- Structural engineering:
- That branch of engineering concerned with the design and construction
of structures to withstand physical forces.
- Sub-bidder:
- One who offers to a bidder on a prime contract a proposal to provide
materials and/or labor.
- Subcontract:
- An agreement between a prime or general contractor and a subcontractor
for the execution of a portion of the contractual obligation of the
prime contractor to the owner.
- Subcontractor:
- A person or organization who has a direct contract with a prime contractor
to perform a portion of the work at the site.
- Subcontractor bond:
- A performance bond given by a subcontractor that guarantees performance
of a contract and the payment of bills for labor and materials.
- Substantial completion:
- Same as date of substantial completion.
- Substitutions:
- Materials or processes offered in lieu of, and as being equivalent
to, specified materials or processes.
- Successful bidder:
- Same as selected bidder.
- Superintendent:
- At a construction site, the contractor's representative who is responsible
for continuous field supervision, coordination, and completion of the
work, and, unless another person is designated in writing by the contractor,
is responsible to the owner and the architect for any accidents.
- Supervision:
- The observation and inspection of construction work to ensure conformity
with the contract documents. Also, direction of work by the contractor's
personnel.
- Supplemental or supplementary conditions:
- Part of the contract documents that supplement and may modify provisions
of the general conditions.
- Surety:
- A person or organization who, for a consideration, promises in writing
to make good the debt or default of another.
- Surety bond:
- A legal instrument under which one party agrees to answer to another
party for the debt, default, or failure to perform by a third party.
- Survey:
- A boundary and/or topographic mapping of a site.
- Tender:
- A proposal or bid for a contract to perform work. It is completed
by a contractor and gives the estimated price and time to complete a
contract. A form is often used.
- Terminal expense:
- An expense incurred in connection with the termination of a contract.
- Time:
- Time limits or period stated in the contract.
- Timely completion:
- Completion of the work or a designated portion of the work on or before
the date required.
- Time of completion:
- The date established in the contract, by name or by number of days,
for substantial completion of the work.
- Title insurance:
- Insurance, offered by a company, that the title to property is clear
or that it may be cleared by curing specified defects.
- Title search:
- An inquiry into the historical ownership record of a property.
- Topographical survey:
- The configuration of a surface, including its relief and the locations
of its natural and man-made features.
- Trade:
- A person's occupation or craft, usually involving manual skill.
- Turn-key job:
- A job in which the contractor completes all work and furnishings of
a building so that it is ready for immediate use.
- Variation order:
- Same as change order.
- Visual inspection:
- Inspection by examination without the use of testing apparatus.
- Waiver of lien:
- An instrument by which a person or organization who has or may have
a right of mechanic's lien against the property of another relinquishes
such right. Same as release of lien.
- Work:
- All labor necessary to produce the construction required by the contract
document.
- Working drawings:
- Drawings intended for use by a contractor, subcontractor, or fabicator,
that form part of the contract documents for a building project.
- Workman's Compensation Insurance:
- Insurance convering liability of an employer to his employees for
compensation and other benefits required by workmen's compensation laws.
- Zoning:
- The control by a municipality of the use of land and buildings, the
height and bulk of the buildings, the density of population, the relation
of a lot's building coverage to open space, size and location of yards
and setbacks, and the provision of any ancillary facilities.
- Zoning permit:
- A permit issued by appropriate government authority authorizing land
use for a specific purpose.

Copyright © 2001-2006 Trans-Management Systems
Corporation. All rights reserved.
Please Note: Links on this site are verified monthly.
While links are evaluated before being included on this site, HSIPC is not responsible for the information presented on external sites.
Last Modified: 06/03/02